Oracle
OracleORCLNYSE
A living review of Oracle, the database and business-software company that has become one of the largest builders of AI data centres - how it makes money, its $664bn of contracts, how it is paying for the build-out and what it says. Updated as the company reports.
This is general information, not financial advice. It does not take your circumstances into account. The value of investments can fall as well as rise and you may get back less than you put in. If you are unsure, speak to an adviser regulated where you live.
Latest results
Latest reported quarter: June to August 2026, the first quarter of Oracle's 2027 financial year (which runs from June 2026 to May 2027). Next results: the second quarter, September to November 2026, date not yet announced (checked 17 November 2026). A year ago Oracle filed the same quarter's report with the SEC on 11 December.
- Revenue: $19.3bn in the quarter, up 30% on a year earlier. Cloud revenue was $11.6bn, up 62%.
- Cloud infrastructure: $7.4bn, up 121% - the renting of computing power, now mostly for AI.
- Operating income: $6.7bn, up 57%; an operating margin of 35%.
- Net income: $4.8bn, up 63%.
- Cash: $23.1bn from operations, including $11.4bn of prepayments from customers, against $28.5bn of capital spending. Oracle puts its free cash flow for the quarter at negative $5bn.
- Contracts: $664bn of remaining performance obligations - revenue customers have signed up for but Oracle has not yet delivered - up $209bn in a year.
- Its own outlook: total revenue of at least $90bn for the year to May 2027, against $67.4bn the year before.
- Leadership: Larry Ellison, executive chair and chief technology officer; Clay Magouyrk and Mike Sicilia, joint chief executives; Hilary Maxson, chief financial officer since 6 April 2026.
Oracle is based in Austin, Texas, and had about 141,000 full-time employees in May 2026. Its financial year runs from 1 June to 31 May and is named after the year it ends in. Figures are in US dollars.
How Oracle makes money
For most of its history Oracle sold database software and the business applications built on it, and charged customers every year for support. That business is still large, but the growth now comes from the cloud:
- Cloud infrastructure (OCI): renting out computing power, storage and networking from Oracle's data centres. This is where the AI demand lands: AI developers rent large clusters of graphics processors (GPUs) to train and run their models.
- Cloud applications: business software delivered over the internet, such as Fusion (finance, HR and supply chains) and NetSuite.
- Software: licences and support for Oracle software that customers run on their own computers. Oracle says this is shrinking as customers move to the cloud.
- Hardware and services: servers and storage, plus consulting and support.
Oracle: revenue by business, quarter to August
- Quarter to Aug 2025
- Quarter to Aug 2026
Show the numbers
| Values ($bn) | Quarter to Aug 2025 | Quarter to Aug 2026 |
|---|---|---|
| Cloud | 7.2 | 11.6 |
| Software | 5.7 | 5.6 |
| Hardware | 0.7 | 0.8 |
| Services | 1.3 | 1.4 |
Cloud was 51% of Oracle's revenue in the year to May 2026, up from 37% two years earlier. Cloud infrastructure made up 84% of that year's cloud growth, at constant exchange rates, according to the annual report.
Results by quarter
Oracle: revenue and net income by quarter
- Revenue
- Net income
Show the numbers
| Values ($bn) | Revenue | Net income |
|---|---|---|
| Nov 2024 | 14.1 | 3.2 |
| Feb 2025 | 14.1 | 2.9 |
| May 2025 | 15.9 | 3.4 |
| Aug 2025 | 14.9 | 2.9 |
| Nov 2025 | 16.1 | 6.1 |
| Feb 2026 | 17.2 | 3.7 |
| May 2026 | 19.2 | 4.3 |
| Aug 2026 | 19.3 | 4.8 |
Show all 4 sources
Revenue grew slowly until late 2025, then picked up as new data centres came into use: up 30% in the latest quarter. Net income in the quarter to November 2025 includes a one-time gain from selling Oracle's stake in Ampere, a chip designer, which is why it stands out.
Oracle: operating margin by quarter
Show the numbers
| Values (%) | Operating margin |
|---|---|
| Nov 2024 | 30 |
| Feb 2025 | 30.8 |
| May 2025 | 32.1 |
| Aug 2025 | 28.7 |
| Nov 2025 | 29.5 |
| Feb 2026 | 31.8 |
| May 2026 | 32 |
| Aug 2026 | 34.8 |
Show all 4 sources
So far the AI business has not pulled margins down: operating margin rose to 35% in the latest quarter. Costs for running the cloud and software business rose 77% in the year, faster than revenue, while sales and marketing and research and development costs fell.
These charts are rebuilt from Oracle's own SEC filings each time it reports. Quarters are labelled by the month they end, as filed.
The contract backlog: $664bn
Oracle's remaining performance obligations jumped from $138bn to $455bn in the quarter to August 2025 and have kept rising. Oracle puts the rise over the latest year down "primarily" to "certain significant cloud contracts":
Oracle: remaining performance obligations by quarter
Show the numbers
| Values ($bn) | Remaining performance obligations |
|---|---|
| Nov 2024 | 97.3 |
| Feb 2025 | 130.2 |
| May 2025 | 137.8 |
| Aug 2025 | 455.3 |
| Nov 2025 | 523.3 |
| Feb 2026 | 552.6 |
| May 2026 | 638 |
| Aug 2026 | 664 |
Show all 5 sources
- Scale: $664bn is nearly ten times Oracle's revenue in the year to May 2026 (our calculation).
- Timing: Oracle expects to recognise about 13% of it as revenue in the next twelve months, 37% in the following two years, 34% in the two years after that, and the rest later.
- Still growing: it booked more than $30bn of new AI cloud contracts in the quarter to August 2026. Oracle says "Customer demand for AI Cloud Training and Inferencing Services continues to grow faster than supply."
- Concentrated: Oracle does not name the customers behind these contracts in its filings, but warns that "In certain OCI offerings, we are more concentrated among a number of large customers".
Spending and paying for it
Delivering those contracts means building data centres first and being paid later. Oracle's capital spending has been larger than its cash from operations in every quarter since February 2025:
Oracle: capital spending against cash from operations
- Cash from operations
- Capital spending
Show the numbers
| Values ($bn) | Cash from operations | Capital spending |
|---|---|---|
| Nov 2024 | 1.3 | 4 |
| Feb 2025 | 5.9 | 5.9 |
| May 2025 | 6.2 | 9.1 |
| Aug 2025 | 8.1 | 8.5 |
| Nov 2025 | 2.1 | 12 |
| Feb 2026 | 7.2 | 18.6 |
| May 2026 | 14.6 | 16.5 |
| Aug 2026 | 23.1 | 28.5 |
Show all 4 sources
- Spending: $55.7bn of capital spending in the year to May 2026, against $32.0bn of cash from operations. $28.5bn more in the quarter to August 2026. Oracle expects capital spending in the year to May 2027 "to be higher than fiscal 2026", the year to May 2026.
- Customer money up front: the latest quarter's cash from operations includes $11.4bn of prepayments from customers. Without them it would have been $11.7bn (our calculation).
- Borrowing: $125.3bn of notes and other borrowings at 31 August 2026. Interest expense was $1.4bn in the quarter, up from $0.9bn a year earlier.
- New shares: Oracle sold $20bn of shares through an "at-the-market" programme in the quarter to August 2026, and $5bn of mandatory convertible preferred shares are outstanding. On 4 November 2026 it completed a further sale of $10bn of shares and $10bn of bonds, paying between 7.0% and 8.65% a year, due between 2029 and 2046.
- Leases: on top of the leases already on its balance sheet ($34.6bn of operating and $9.2bn of finance lease liabilities), Oracle has signed $288bn of data-centre leases that have not started yet. They are expected to begin between late 2026 and May 2029 and run for 15 to 19 years.
- The plan: at its Investor Day on 28 October 2026, Oracle said capital spending would peak in its 2027 and 2028 financial years (June 2026 to May 2028), that free cash flow would turn positive in the second half of its 2028 financial year (December 2027 to May 2028), and that it would limit new money raised in the markets up to May 2030 to $20bn - $10bn of shares and $10bn of debt, not counting refinancing. The 8-K for the November sale does not say whether it counts against that limit.
For how Oracle compares with Microsoft, Alphabet, Amazon and Meta, see the capex gauge on the home page and the AI bust watch.
Who it depends on
- A few very large AI customers. The contracts that lifted the backlog are concentrated, and Oracle warns that "some of our customers may be highly leveraged", with risks of "non-payment and non-performance".
- Chips and power. Its data-centre expansion depends on build sites, "reliable and predictable power sources", networking equipment and GPUs. It says supply of AI chips and memory is tight, and "we at times have to accept less favorable terms with suppliers", which has "increased excess and obsolescence risk" for that hardware.
- Lenders and landlords. Oracle says a cut in its credit rating could raise its borrowing costs and "affect the terms or availability of certain long-term commitments (including data center leases)".
- Building on time. It lists delays and cost increases in design, permitting, construction and connection to the grid, and "Government-imposed limits or moratoria on data center construction".
- Its older business. Software licences and support, still $5.55bn in the latest quarter, fell 3% as customers move to the cloud.
Outlook
Two kinds of projection, kept apart. Neither is ours.
1. Oracle's guidance for its next quarter (to 30 November 2026): total revenue growth of 30% to 34%, and cloud revenue growth of 65% to 71% in US dollars. For the year to May 2027: total revenue of at least $90bn, about 34% more than the year before (our calculation).
2. Oracle's longer-term targets (Investor Day, 28 October 2026): total revenue of $225bn or more in the year to May 2030, more than 35% a year growth from the year to May 2026; free cash flow of $30bn or more in the year to May 2029; and borrowing, net of cash, below 3.5 times its adjusted earnings before interest, tax, depreciation and amortisation in that year.
Company guidance can be wrong, and Oracle's own filings list the risks. We do not publish share-price targets or ratings.
In Oracle's own words
- Results release, 10 September 2026: "Customer demand for AI Cloud Training and Inferencing Services continues to grow faster than supply."
- Results release: Oracle "delivered more than 300,000 GPUs to its AI Cloud customers" since the end of May 2026.
- Quarterly report: "we have flexibility in managing the timing of certain discretionary capital expenditures."
- Investor Day: "Vendor financing, customer-provided hardware and customer prepayments are expected to reduce upfront cash requirements through the transition to positive free cash flow."
The verdict
This is our reading of the business, not a forecast and not a view on the shares. It will be revisited after every results release.
Oracle has turned from a steady software company into one of the biggest bets on AI demand. It has signed contracts worth nearly ten times a year's revenue, and is borrowing, selling shares and taking customers' money up front to build the data centres needed to deliver them.
- The demand is signed. $664bn of contracts, still rising, and cloud infrastructure revenue more than doubling in a year.
- The profits are holding up so far. Operating margin rose to 35% in the latest quarter.
- The cash is not there yet. Capital spending has exceeded cash from operations in every quarter since February 2025, and Oracle does not expect positive free cash flow before December 2027 to May 2028, the second half of its 2028 financial year.
- The risk is concentration. A few large AI customers, some of them "highly leveraged" in Oracle's own words, stand behind much of the backlog, while Oracle carries the debt, the leases and the hardware.
What would change this reading:
- New contracts slowing, or existing ones being cut or delayed by customers.
- Capital spending staying high beyond May 2028, the end of Oracle's 2028 financial year, or more money raised than the $20bn limit.
- A cut in Oracle's credit rating.
- Cloud infrastructure margins falling as more capacity comes online.
What to watch
- Second-quarter results (December 2026, date to be announced): revenue against the 30% to 34% growth guidance, the backlog, capital spending and customer prepayments.
- Free cash flow, against the plan to turn positive between December 2027 and May 2028.
- Lease start dates: how fast the $288bn of signed data-centre leases begin.
- Its largest customers' own funding, since they pay for the contracts. See Who is paying for the AI build-out? and the AI bust watch.
Update log
- 17 November 2026: page created. Covers results to the quarter ending 31 August 2026, the annual report filed on 22 June 2026, the Investor Day of 28 October 2026 and the share and bond sale completed on 4 November 2026.
Disclosure: this page was drafted with help from Claude, an AI model made by Anthropic. Anthropic has no part in what we publish; every fact here is taken from the filings and statements listed under Sources.
Drafted with help from an AI tool, then checked and edited by a person. Sources are listed below.
Sources (13)
- Oracle Q1 fiscal 2027 results, SEC Form 8-K Exhibit 99.1 (10 September 2026) - checked
- Oracle Form 10-Q for the quarter to 31 August 2026 (SEC EDGAR) - checked
- Oracle Form 10-K for the year to 31 May 2026 (SEC EDGAR) - checked
Show all 13 sources
- Oracle Investor Day 2026, SEC Form 8-K Exhibit 99.1 (28 October 2026) - checked
- Oracle Form 8-K, issuance of $10bn of common stock and $10bn of notes (4 November 2026) - checked
- Oracle appoints Hilary Maxson as Chief Financial Officer, SEC Form 8-K Exhibit 99.1 (6 April 2026) - checked
- Oracle investor relations, events and presentations - checked
- Oracle 10-Q filed 11 December 2025 (SEC EDGAR) - checked
- Oracle 10-Q filed 11 March 2026 (SEC EDGAR) - checked
- Oracle 10-K filed 22 June 2026 (SEC EDGAR) - checked
- Oracle 10-Q filed 11 September 2026 (SEC EDGAR) - checked
- Oracle Form 10-Q for the quarter to 31 August 2025 (SEC EDGAR) - checked
- Oracle Form 10-Q for the quarter to 30 November 2024 (SEC EDGAR) - checked